Progress Payments in Construction: What Contractors Need to Know

ePROMIS Solutions7 min read

Concerns about cash flow are a significant worry for construction companies and contractors. These businesses typically lay out significant funds for project-related expenses and don't get paid until the job is complete. For smaller firms with limited cash reserves, this can be especially challenging, particularly for long-term projects.

An alternative method involves receiving payments at predefined stages or percentages of project completion, referred to as "progress payments." This guide explains the workings of progress payments and their benefits for all parties involved.

What Is a Progress Payment?

In the construction industry, a progress payment is a partial payment made to a business or contractor after the completion of a predefined stage of work, such as a demolition or the addition of a roof and siding. These installments replace other approaches, like a single lump-sum payment at the end of a project or a “half upfront, half at the end” arrangement.

Progress payments help companies recover a portion of their costs throughout a project, maintaining steady cash flow. They also protect companies in the case of client nonpayment; a firm may decide to stop working on a project until payment issues are resolved. On the other side, progress payments give clients a chance to assess whether the billed portion of work meets their satisfaction before proceeding. This incremental approval approach can help preempt problems.

How Do Progress Payments Work?

Progress payments are determined by the completion of specific portions or percentages of work. These milestones are defined and agreed upon by all parties involved—client, bank or other funders, and contractor—when the construction contract is signed. Key considerations include determining and scheduling the intervals for invoicing payments, specifying what each payment will cover, and setting the payment due dates.

Progress payments alleviate the cash-flow burden on contractors, who otherwise would have to front all the money for a construction project and then wait long periods to recoup expenses and make a profit. They also mitigate the risk of a project client declaring bankruptcy or a bank withdrawing funding, which could leave the contractor without payment.

How Are Progress Payments Determined?

Progress payments can be set up in several ways. The most common methods are based on when a designated stage of a project is completed, as when plumbing and electrical are in place; a certain percentage of the project being done, such as 25% completion; or a designated period of time, such as monthly.

The method chosen generally depends on a project's complexity, the necessary outlay of expenses, and the impact on the business's cash flow.

Construction Pricing Structures

Construction businesses have various ways to price and get paid for their work. The method selected typically depends on the project type involved.

The most common construction pricing structures are:

  • Time and Material (T&M) Pricing: Used when the job's scope or duration can't be determined before work begins. T&M pricing establishes fixed quotes for labor rates, a maximum number of labor hours, and the cost of materials (including freight) and specified markup. Payment milestones, aka progress payments, are set. Invoicing is relatively quick and easy since rates are pre-determined, though construction firms need to stay on top of record-keeping and receipts.
  • Lump-Sum Pricing: Establishes a fixed price to be paid upon project completion. This method is typically limited to jobs where estimating total costs is straightforward. This model is also common with smaller projects involving less time, work, and associated expenses.
  • Cost-Plus Pricing: Covers the actual costs of construction (direct expenses and overhead), plus an agreed-on profit amount usually based on a percentage of direct expenses. Thorough record-keeping and documentation are vital to verify expenses. Cost-plus contracts are often written to pay out based on project progress.
  • Unit Pricing: Establishes prices for individual portions of work, including costs for materials, labor, and overhead. This pricing is useful for projects that can be easily and logically split into work bundles, especially when the final scope is unclear.

Why Are Progress Payments Important in Construction?

Construction firms often pay for materials and labor upfront, waiting until the project's completion to get paid. This can strain a business's finances, particularly smaller firms. Progress payments provide a steady influx of money to cover costs and invest in the next project phase or start a new one.

Progress payments serve other crucial roles throughout the construction chain. They help track progress and that of subcontractors, especially with project accounting or management software. Payment applications, similar to invoices, reviewed by clients, can detect and address work quality issues promptly before the project advances.

Progress payments also encourage project momentum. The more work completed toward the next milestone, the closer the company gets to the next payment. Additionally, progress payments offer financial protection for all parties if an unforeseen event halts a project, such as a fire, a business going bankrupt, or a pandemic.

How to Bill for Progress Payments

The construction industry uses a payment application to bill clients. A payment application is more than a simple invoice; it includes a schedule of values, progress reports of completed work and materials delivered, subcontractor invoices, a timetable of remaining work, and photos and payroll receipts.

General contractors commonly use the AIA G702 form from the American Institute of Architects, while subcontractors may use either this form or the ConsensusDocs 710. The construction contract should specify which form is required. The payment application must be completed promptly and delivered to the payor. Additionally, payment applications should be notarized.

Benefits of Progress Payments

Construction businesses, contractors, subcontractors, and project owners benefit from being paid in installments based on predefined stages of project completion. Key benefits include:

  • Stable Cash Flow: Progress payments provide a steady income stream, reducing the working capital needed as a project advances. This makes it easier to cover supply and labor costs, lessening the chance of debt to finance a project.
  • Source of Motivation: Being paid for work is a great motivator. Progress payments can drive productivity, reduce material and labor expenses, and result in higher profits in an industry with traditionally small margins.
  • Potential Payment Problems: If payments are late or not received, it could indicate the client is experiencing financial issues. Progress payments help flag this early on, possibly preventing legal action.
  • Time to Pause: If a client doesn't pay for completed work, a company may pause work until the issue is resolved and payment is received. The construction contract should outline stipulations regarding this tactic in dispute resolution.

Drawbacks of Progress Payments

Despite the advantages, progress payments have some disadvantages contractors should be aware of:

  • More Payments, More Accounting: Construction firms must ensure they are paid, and many don't have a dedicated financial department. Progress payments mean tracking and processing multiple payments, assuming a client pays without incident. Subcontractors also need to be paid for each work installment.
  • Disputes Over Work: Owners and contractors may disagree on the work completed. For example, a contractor may submit an invoice for 50% completion, but the owner believes only 40% is done and pays accordingly. This can financially hurt the contractor and delay project completion, affecting future payments. Clear contracts and constant communication are crucial.

How Does Retainage Impact Progress Payments?

Withholding a percentage of payment until project owners ensure work is completed correctly, called retainage or retention, is common in the construction industry. The amount held back, often 5%-10%, should be specified in the contract. Retainage is typically deducted from each progress payment and released upon project completion or a specified period afterward. Some contracts allow partial retainage payments before project completion.

Manage Progress Payments with Accounting Software

Construction projects require extensive financial and accounting work. Cloud-based software solutions, such as ePROMIS financial management software, meet the needs of construction businesses of all sizes. ePROMIS accounting software automates invoicing, including retainage line items, and tracks payments, easing the burden on contractors. ePROMIS Billing invoice and billing management software creates, manages, and supports recurring billing operations, including progress payments. Billing provides full integration with advanced revenue management and compliance. It also lets contractors standardize forms across all projects, including payment applications. Streamlined and efficient tasks free resources for client-facing aspects of a construction business.

Construction projects require significant outlays of money to start. Job materials must be ordered and shipped, and subcontractors and crews must be paid. Rather than waiting for a lump-sum payment at the project's end, progress payments allow construction firms and contractors to bill in installments after completing predetermined stages or percentages of work. All parties benefit from this arrangement. Construction companies maintain steady cash flow, while project owners review completed work portions and ensure satisfaction before payment. Project management and accounting software help move the entire payment process and the construction project forward.

Share